Category: HL-LHC News

  • Validation of the second Cold Powering System for HL-LHC

    Validation of the second Cold Powering System for HL-LHC

    Following the successful qualification of the first Cold Powering System for the Inner Triplets (the new quadrupoles that will be either side of the interaction points at Points 1 and 5)

    Explore →

  • Annual HL-LHC Newsletter Released !

    Annual HL-LHC Newsletter Released !

    In this critical time for the HL-LHC Project, with all teams – at CERN and our numerous collaborators – working towards Long Shutdown 3, we take a look at the progress of the past year in the annual project newsletter.

    Explore →

  • HL-LHC Helium cryogenic plants enters installation phase

    HL-LHC Helium cryogenic plants enters installation phase

    As of early June, the HL-LHC Cryogenics project reached a new important milestone with the launch of installation activities for the helium refrigeration plants. Two helium cryogenic plants—each delivering 14 kW equivalent at 4.5 K,

    Explore →

  • Powering Future Accelerators

    Powering Future Accelerators

    Klystrons are key components in the development of future energy-efficient colliders. The latest edition of the CERN Courier magazine explores their recent developments.

    Explore →

  • First HL-LHC Beam Position Monitor ready for installation

    First HL-LHC Beam Position Monitor ready for installation

    This May, the first Beam Position Monitor (BPM) for the HL-LHC finished its in-house production in the CERN ateliers. The BPM is now ready for assembly with the new beam screen and will be installed in the first HL-LHC Inner Triplet cryomagnet (Q1).

    Explore →

  • New RF Springs for HL-LHC double-beam collimators

    New RF Springs for HL-LHC double-beam collimators

    By Lucas Hermida Pena (CERN) Collimators are Beam Interaction Devices (BIDs) designed to remove stray particles from the beam bunches which could damage sensitive equipment. Recently, two fully functional prototype double-beam collimators were fitted with new radiofrequency springs and then installed onto the assembly mock-up. In the current LHC, all collimators are single-beam, but these…

    Explore →

  • First batch of jacks for HL-LHC delivered at CERN

    First batch of jacks for HL-LHC delivered at CERN

    In March 2025, CERN received the first batch of jacks required to support and remotely align the HL-LHC magnets, TAXN absorbers, and crab cavity cryomodules.

    Explore →

  • Final resistive parts of current leads for HL-LHC cold powering systems completed at CERN

    Final resistive parts of current leads for HL-LHC cold powering systems completed at CERN

    At the end of February, the final resistive parts for the current leads for HL-LHC Cold Powering Systems (WP6A) were completed at CERN by EN-MME.(WP6A) were completed at CERN by EN-MME.

    Explore →

  • First RFD cold test at TRIUMF, Canada

    First RFD cold test at TRIUMF, Canada

    By Florence Thompson (CERN) and Bob Laxdal (TRIUMF) The HiLumi Project Canadian contribution is now really kicking off with the reception of the first prototype RFD cavity, contributed by the US-AUP collaboration.

    Explore →

  • Robotic solution: successful preparation of the CMS rotating shielding for future HL-LHC vacuum module installation

    Robotic solution: successful preparation of the CMS rotating shielding for future HL-LHC vacuum module installation

    The CMS rotating shielding has now been successfully modified in-situ to prepare it to receive new vacuum modules for the HL-LHC, using a specifically designed method to deal with the space and radiation constraints of this complex manoeuvre.

    Explore →