Accelerator Report: Linac4 beam commissioning is nearing completion and the PS Booster is next in line
While the first H⁻ ion beams have been accelerated up to 160 MeV in Linac4, the PS Booster is preparing for its first proton injection of 2025.
By Rende Steerenberg

As I write, the hardware re-commissioning of the PS Booster (PSB), which began on 13 February, is progressing well and remains on schedule – the injection of the first 2025 proton beam into the PSB is planned for 27 February. From that point onward, Linac4 should be fully operational, providing beams to the PSB in a stable and reliable way, ready for an efficient PSB beam commissioning.
Meanwhile, on 22 February, the hardware re-commissioning of both the Proton Synchrotron (PS) and the Super Proton Synchrotron (SPS) also began. The two accelerators are on track to receive their first proton beams and begin beam commissioning on 5 March and 14 March, respectively…